M-6 Hyderabad-Sukkur Motorway still at procurement stage; N-25 Karachi-Chaman at 19% after review
Ahsan Iqbal has told the NHA to clear bottlenecks on the country's biggest road projects. Here is where each one stands, from the Rs 363.7 billion M-6 to the Shandur-Gilgit road.
The 306 km Hyderabad-Sukkur Motorway (M-6), with an approved cost of Rs 363.7 billion, has still not moved past the procurement stage, Planning Minister Ahsan Iqbal was told on Friday at a review of National Highway Authority projects. He directed the NHA to remove procedural bottlenecks and speed up procurement on the M-6 and on the electrical and mechanical works of the Lowari Tunnel, ARY News reported.
The M-6 is the missing link between the Karachi-Hyderabad M-9 and the motorways north of Sukkur. Until it is built, traffic between Karachi and Punjab on the motorway network has to use the National Highway (N-5) through interior Sindh.
Where each project stands
| Project | Length | Cost (Rs billion) | Status |
|---|---|---|---|
| M-6 Hyderabad-Sukkur Motorway | 306 km | 363.70 | Procurement |
| Lowari Tunnel, electrical and mechanical works | n/a | 33.25 | Procurement |
| N-25 Karachi-Quetta-Chaman dualisation | 273 km | 183.42 | 19.25% built |
| Shandur-Gilgit Road | 216 km | 49.95 | 67.33% built |
| Chitral-Booni-Mastuj-Shandur Road | 153 km | 17.78 | 40% built |
| N-55 Shikarpur-Rajanpur second carriageway | 221.9 km | 44.70 | 62% built |
| N-55 Rajanpur-Dera Ghazi Khan | 121.5 km | 63.15 | Awaiting award (land acquisition) |
| N-55 Dera Ghazi Khan-Dera Ismail Khan | 208.19 km | 111.94 | Awarded, contractors mobilising |
| N-50 Yarik-Sagu-Zhob with Zhob Bypass | 210 km | 76.49 | 10% built |
Figures as presented to the minister, rounded to two decimals.
What the minister ordered
- Faster work on the N-25, especially the Karachi-Kararo and Wadh-Khuzdar sections, which carry much of the trade traffic to Quetta and Chaman.
- No unexplained cost increases. Contractors' claims for extra payment must go through technical, contractual and financial scrutiny, with independent third-party checks of costs, quality and quantities.
- A list of projects that a small extra allocation could finish.
- Proposals within 15 days on the outstanding financial claims related to the bypass project.
- Action plans with deadlines for projects held up by money or administrative problems.
What it means for you
For drivers in Sindh and Balochistan, the review confirms that the two biggest promises on the southern road network are still years away: the N-25 dualisation is less than a fifth done, and the M-6 has not yet been contracted. The N-55 Indus Highway between Shikarpur and Rajanpur, at 62%, is the nearest to completion.
Planning a long drive meanwhile? Our fuel cost calculator works out the cost of a trip at today's petrol price.
Frequently asked questions
- When will the Hyderabad-Sukkur Motorway (M-6) be built?
- As of 30 October 2026 the 306 km M-6, with a PC-I cost of Rs 363.7 billion, was still at the procurement stage, so construction had not started.
Sources
Related reading
Pakistan
Iqbal Day 2026: Monday 9 November is a public holiday across Pakistan
The Cabinet Division listed Allama Iqbal's birthday as a national holiday in its 2026 calendar, so government offices close on Monday 9 November and many people get a three-day weekend.
3h ago

Reader comments 0
No comments yet. Say something useful.